After reviewing the work performance data you have requested a change from the change control board. What could have led to this change?

After reviewing the work performance data you have requested a change from the change control board. What could have led to this change? (Choose 2) A. SPI = 1.2 B. CPI = .8 C. SPI = 1 D. CPI = 1.5 E. SPI = .5

1 Answer

Verified archive
AnonymousJune 1, 2024

B and E. SPI and CPI should always be >= 1. Anything below 1 signals an issue.