You have taken over a project during project planning and have discovered that six individuals have signed the project charter. Which of the folowing should most concern you?
A. who will be a member of the CCB
B. Spending more time on configuration management
C. Getting a single project sponsor
D. determining the reporting structure
B. Spending more time on configuration management