To manage risk for an agile project, which of the following would you be least likely to need?
A. Risk burndown chart
B. Risk-adjusted backlog
C. Risk management plan
D. Risk-based spike
To manage risk for an agile project, which of the following would you be least likely to need?
A. Risk burndown chart
B. Risk-adjusted backlog
C. Risk management plan
D. Risk-based spike
C. Risk management plan.
The other choices here are all great ways of managing risk in agile.