A PM has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process.
A. Earned Value analysis
B. Schedule change control system
C. Trend analysis
D. Reserves
A PM has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process.
A. Earned Value analysis
B. Schedule change control system
C. Trend analysis
D. Reserves
D. Reserves
In the Develop Schedule process, reserves (both contingency and management reserves) are essential to account for uncertainties and potential risks that might affect the project schedule. These reserves help ensure that the schedule is realistic and achievable, even if unexpected issues arise.