Quizzma Latest Questions

While working on an agile project, a team member has informed the PM of potential personal issues that could lead to him being out ofr the next six weeks. This might cause a delay in the work. What should the PM do first in this situation?

Anonymous

While working on an agile project, a team member has informed the PM of potential personal issues that could lead to him being out ofr the next six weeks. This might cause a delay in the work. What should the PM do first in this situation?

A. Ask the team member to stay

B. Meet with the other team members and inform them of this potential issue

C. Inform the project sponsor right away

D. Start looking for a 6-week replacement




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. B. The first step will be to update the team members before taking any action. This is a risk/threat, not an issue yet.