To manage risk for an agile project, which of the following would you be least likely to need?
A. Risk burndown chart
B. Risk-adjusted backlog
C. Risk management plan
D. Risk-based spike
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
C. Risk management plan.
The other choices here are all great ways of managing risk in agile.