Quizzma Latest Questions

To manage a project effectively, work should be broken down into small pieces. Which of the following does NOT describe how far to decompose the work?

To manage a project effectively, work should be broken down into small pieces. Which of the following does NOT describe how far to decompose the work?

A. until it has a meaningful conclusion

B. until it cannot be logically subdivided further

C. until it can be done by one person

D. until it can be reasonably estimated




Leave an answer

Leave an answer

1 Answer

  1. C. until it can be done by one person

    Work packages in the WBS can be completed by more than one person. The other answers are correct

Related Questions