The program was planned years ago, before there was a massive introduction of new tech. While planning the next project in this program, the PM has expanded the scope management plan because as a proect becomes more complex, the level of uncertainty in the scope

The program was planned years ago, before there was a massive introduction of new tech. While planning the next project in this program, the PM has expanded the scope management plan because as a proect becomes more complex, the level of uncertainty in the scope:

A. remains the same

B. decreases

C. decreases then increases

D. increases

1 Answer

Verified archive
AnonymousJune 6, 2024

D. increases

Added complexity = added uncertainty