Quizzma Latest Questions

The WBS and WBS dictionary have been completed, and the project team has begun working on identifying risks. The sponsor contacts the PM requesting that the responsibility assignment matrix be issued. The project has a $100,000 budget and is taking plact in 3 countries with 14 human resources. There is little risk expected, and the PM has managed many project simiar to this one. What is the next thing to d?

Anonymous

The WBS and WBS dictionary have been completed, and the project team has begun working on identifying risks. The sponsor contacts the PM requesting that the responsibility assignment matrix be issued. The project has a $100,000 budget and is taking plact in 3 countries with 14 human resources. There is little risk expected, and the PM has managed many project simiar to this one. What is the next thing to d?

A. Understand the experience of this sponsor on similar projects

B. Create an activity list

C. Make sure the project scope is defined

D. Complete risk management and issue the responsibility assignment matrix




Leave an answer

Leave an answer

1 Answer

  1. B. Create an activity list

    This is all about understanding order of operations. Activity list comes next after WBS and WBS Dictionary.

Related Questions