The high level project schedule constraints have just been determined. What PM process group are you in?

The high-level project schedule constraints have just been determined. What PM process group are you in?

A. initiating

B. planning

C. executing

D. monitoring and controlling?

1 Answer

Verified archive
Quizzma TeamJune 3, 2024

This is defined in the project charter during initiating phase.

Answer: A. initiating.