The program was planned years ago, before there was a massive introduction of new tech. While planning the next project in this program, the PM has expanded the scope management plan because as a proect becomes more complex, the level of uncertainty in the scope:
A. remains the same
B. decreases
C. decreases then increases
D. increases
D. increases
Added complexity = added uncertainty