The PM is owrking to clearly describe the level of involvement expected from everyone on the project in order to prevent rework, conflict, and coordination problems. Which of the following best describes the PMs efforts?

Anonymous

The PM is owrking to clearly describe the level of involvement expected from everyone on the project in order to prevent rework, conflict, and coordination problems. Which of the following best describes the PMs efforts?

A. Develop project management plan and plan quality management

B. Manage stakeholder engagement and direct and manage project work

C. Validate scope and control quality

D. identify risks and develop project team




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. A. Develop project management plan and plan quality management.

    Notice that this describes something in the planning stage. This sounds like project planning