Quizzma Latest Questions

Several successor activities are behind schedule because a project team member has not been at work for the past week. This impacts the critical path. How should the project manager respond to this problem?

Anonymous

Several successor activities are behind schedule because a project team member has not been at work for the past week. This impacts the critical path. How should the project manager respond to this problem?




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. Discuss the situation with the team member, and work with them to identify a practical solution.

    A Project Manager also has the ability to be a mentor/coach. Servant Leadership encourages listening and serving, and therefore it may be possible to compromise with the team member.