Several successor activities are behind schedule because a project team member has not been at work for the past week. This impacts the critical path. How should the project manager respond to this problem?
Question & Answer
Several successor activities are behind schedule because a project team member has not been at work for the past week. This impacts the critical path. How should the project manager respond to this problem?
1 Answer
Verified archiveDiscuss the situation with the team member, and work with them to identify a practical solution.
A Project Manager also has the ability to be a mentor/coach. Servant Leadership encourages listening and serving, and therefore it may be possible to compromise with the team member.