During a hybrid project a client requests that a new product feature be added. This feature will add to the scope and cost. What should the PM do first in this situation to determine who can approve his request?
A. Review change log
B. Review change management plan
C. Review Responsible, accountable, consult, and inform (RACI) matrix
D. Review the change request document
B. Change log is just a document for tracking changes. RACI is more about team members. Change request document is details changes, not approval.