Consider the following information for a new project: assumptions, preliminary scope, restrictions. After receiving this information, what should the project manager do first?

Anonymous

Consider the following information for a new project: assumptions, preliminary scope, restrictions. After receiving this information, what should the project manager do first?

A. Determine the project goals and business case

B. Choose the project team and assign them tasks

C. Select the project schedule and define critical path

D. Get approval for the project management plan




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. Answer: A.

    Determine the project goals and business case. Reason: before any other tasks can be done, including the project charter, the PM must understand the goals and business case of the project.