During a technical agile project, a well-liked project member is reassigned to a different project. The team has expressed disapproval regarding the reassignment. What action can help mitigate the team's disapproval?

During a technical agile project, a well-liked project member is reassigned to a different project. The team has expressed disapproval regarding the reassignment. What action can help mitigate the team’s disapproval?

A. Notify the project sponsor regarding the team’s disapproval. Brainstorm a response.

B. Employ leadership and emotional intelligence tools and techniques to inspure the team to continue working.

C. Add a resource with the same skills to replace the key team member.

D. Notify the change control board (CCB) and discuss possible ways to resolve the issue.

1 Answer

Verified archive
AnonymousJune 1, 2024

Answer: B

Reason: The PM should support the team as a servant leader and help them to stay motivated and productive. Never go to the sponsor for a response, focus on the team, and don’t kick the can up the road.