An agile project has stakeholders in many countries. The PM is informed by one of the team members that they were approached by a senior manager for project info. What should the PM do next?
A. Consult the stakeholder register.
B. Consult the project management information system (PMIS)
C. Personally invite the senior manager to the next team meeting
D. Review the communications management plan