Question & Answer

Deliverables on the critical path are lagging behind schedule, so the critical path for an IT project is behind schedule. With a CPI of 1.3, the PM gets the project back on schedule by adding new resources. What happens to the project?

Deliverables on the critical path are lagging behind schedule, so the critical path for an IT project is behind schedule. With a CPI of 1.3, the PM gets the project back on schedule by adding new resources. What happens to the project?

A. Activities will be done in parallel.

B. Scope will be revised.

C. Costs and risks will increase.

D. Rework is likely to be necessary

0 Answers

Verified archive

No archived answer is available yet. Quizzma AI can explain it now.