“A PM is putting together a team that includes resources from multiple time zones. Applying for visas has taken longer than expected. What should the PM do?
A. Motivate the team to work longer hours
B. Make a change request regarding the project scope
C. Postpone the project until the visas are under control
D. Suggest virtual work for the appropriate resources”
Suggest virtual work for the appropriate resources