Which action should a PM take to mitigate a schedule delay on a project with a 21% buffer for cost overruns caused by the current software vendor?
A. Access other software vendors that may contribute to project deliverables
B. Replace the current vendor and request a contract from the new vendor
C. Have the vendor meet to discuss legal issues
D. Tolerate the cost overrun and revise the project schedule