Question & Answer

Which action should a PM take to mitigate a schedule delay on a project with a 21% buffer for cost overruns caused by the current software vendor?

Which action should a PM take to mitigate a schedule delay on a project with a 21% buffer for cost overruns caused by the current software vendor?

A. Access other software vendors that may contribute to project deliverables

B. Replace the current vendor and request a contract from the new vendor

C. Have the vendor meet to discuss legal issues

D. Tolerate the cost overrun and revise the project schedule

1 Answer

Verified archive
AnonymousJune 1, 2024

A. Access other software vendors that may contribute to project deliverables

Further assessment is needed before any action can be taken. Replacement, legal threats, or revising the project schedule are all direct actions and we don’t have enough information.