Your project is behind schedule, with only 80% complete of an expected 95%. The total project budget is $140,000 and the actual cost of (AC) is $95,000. What is the schedule performance index (SPI) and the cost performance index (CPI) of the project?
Your project is behind schedule, with only 80% complete of an expected 95%. The total project budget is $140,000 and the actual cost of (AC) is $95,000. What is the schedule performance index (SPI) and the cost performance index (CPI) of the project?
Share
SPI = 0.84 CPI = 1.17 Reason: Earned Value (EV) = Actual percentage BAC = 0.8 $140,000 = $112,000 Planned Value (PV) = Plan percentage BAC = 0.95 $140,000 = $133,000 SPI = EV/PV = 112,000/133,000 = 0.84 CPI = EV/AC = 112,000/95,000 = 1.17