Your project is behind schedule, with only 55% complete of an expected 70%. The total project budge is $210,000, and the actual cost is $162,000. What is the scheduled performance index and the cost performance index?

Anonymous

Your project is behind schedule, with only 55% complete of an expected 70%. The total project budge is $210,000, and the actual cost is $162,000. What is the scheduled performance index and the cost performance index?




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. SPI = 0.79 CPI = 0.71. EV = Actual% BAC = .55 $210,000 = $115,500. PV = Plan% BAC = .77 210,000 = $147,000. SPI = EV/PV = 115,000/147,000 = .79. CPI = EV/AC = 115,500/162,000 = .71