Your company plans to introduce a new product to their development process. The PM has determined that the component work packages have been defined and constraints for each component have been selected. Which estimating technique should the PM use to acquire a precise cost estime of the project?
A. Analagous
B. Three point
C. Bottom-up
D. Paramtetric
C. Bottom Up.
Because the work packages are well defined, bottom-up will be the most accurate prediction tool.