You are a PM on a $5 million dev project. While working with your project team to develop a network diagram, you notice a series of activites that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
A. Precedence diagramming method
B. Arrow diagramming method
C. Critical path method
D. Operational diagramming method
A. Precedence diagramming method
The Precedence Diagramming Method (PDM) is used to construct a project schedule network diagram that shows the relationships among activities. In PDM, activities are represented by nodes and are connected by arrows that depict the dependencies. This method is well-suited for identifying parallel activities that must finish in a specific sequence.