Why does the agile approach plan the work continuously throughout the plan?
A. Agile methods break down the work into small chucks so the team can comlete one iteration at a time.
B. An agile product owner can’t know what they really need until they see a prototype in action
C. Agile teams are asked to prioritize tasks that deliver value, rather than spending their time planing
D. Agile projects are subject to uncertainty and high rates of change that make upfront planning inefficient
Inherent uncertainty and the welcoming of change necessitate frequent planning and iterative work. Answer: Agile projects are subject to uncertainty and high rates of change that make upfront planning inefficient.