The WBS, estimates for each work package, and the network diagram are completed. The next thing for the PM to do is:

Anonymous

The WBS, estimates for each work package, and the network diagram are completed. The next thing for the PM to do is:

A. Sequence the activities

B. Validate that they have the correct scope

C. Create a prelimiary schedule and get the team’s approval

D. Complete risk management




Leave an answer

Leave an answer

1 Answer

  1. C. Create a preliminary schedule and get the team’s approval

    Once the WBS, estimates for each work package, and the network diagram are completed, the next step is to develop a preliminary schedule. This schedule should then be reviewed and approved by the team to ensure that it is realistic and achievable based on the available information and the team’s input.