The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the PM to do?
A. Compress the schedule to recover the two weeks
B. Cut scope to recover the two weeks
C. Consult with the sponsor about options
D. Advise the client of the impact of the change
D. Advise the client of the impact of the change.
Before making any decisions or taking actions, it is crucial for the PM to communicate transparently with the client about the implications of the requested change. This involves:
By advising the client of the impact, the PM can ensure that the client fully understands the ramifications of the requested change before making an informed decision. This transparency and open communication can help manage expectations and align stakeholders.
The other options may be premature or incomplete:
A. Compressing the schedule: While this may be an option, it should not be done without first consulting with the client and fully understanding their priorities and willingness to accept potential trade-offs or risks associated with schedule compression.
B. Cutting scope: Similar to schedule compression, reducing scope may be a viable option, but it should not be done unilaterally without consulting the client and sponsor first.
C. Consulting with the sponsor: While consulting with the sponsor is important, the immediate priority should be to advise the client, who requested the change, of the impact before seeking guidance from the sponsor.
C. Consult with the sponsor about options.
This is part of the mindset. Evaluation and information gathering before acting