On an agile project, a few of the customers informe the team of a feature that was missing a critical function. This has led to the component being redone. What should the team do to prevent this from occurring again?

On an agile project, a few of the customers informe the team of a feature that was missing a critical function. This has led to the component being redone. What should the team do to prevent this from occurring again?

A. Have them prioritize the product backlog

B. Have them define the definition of done

C. Invite them to the sprint planning meeting

D. Inform them the critical function was not needed




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. B. Have them define the definition of done

    The key problem here is user stories, deliverables, and a lack of a definition of done. If customers and team understand the definition of done before a build, this will be avoided.