Quizzma Latest Questions

In managing your first agile project, you are trying to decide how to best keep the sponsor and other key stakeholders updated about the team's progress. You want to use one or more of the agile tools that your team is already maintaining for their own use, rather than asking the team to create any additional status reports or projet documentation. Which agile tool(s) should you use for this purpose?

Anonymous

In managing your first agile project, you are trying to decide how to best keep the sponsor and other key stakeholders updated about the team’s progress.

You want to use one or more of the agile tools that your team is already maintaining for their own use, rather than asking the team to create any additional status reports or projet documentation.

Which agile tool(s) should you use for this purpose?

A. The project roadmap and story maps

B. The task board with WIP limits

C. The velocity burndown matrix

D. The cumulative flow diagram




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. D. There is no such thing as a velocity burndown and the other two metrics don’t track progress over time