CPI is 1.13 and benfit/cost ratio is 1.2 The project scope was created by the team and stakeholder. Requirements have been changing throughout the project. No matter what the PM has tried to accomplish in managing the project, which of the following is she most likely to face in the future?
A. having to cut costs on the project and increase benefits
B. making sure the customer has approved the project scope
C. not being able to measure completion of the product or the project
D. having to add resources to the project
C. not being able to measure completion of the product or the project
The frequent changes in requirements indicate scope creep, which can lead to difficulties in defining clear metrics for project and product completion. This challenge arises because the constant changes can disrupt the original plan and make it hard to track progress and determine when the project or product has been fully completed.