Congratulations! You have just closed your first project in this new organization! A key responsibility of the project manager when closing the project is to provide relevant and correct documentation for lessons learned and organizational knowledge bases/archives.
You work for a supportive PMO, so the documentation needed during closing is not prescribed.
As a project manager obtaining formal closure, which of the following documents would you need to complete before obtaining formal acceptance of closure from the Sponsor? (Choose 2.)
1. A lessons learned report
2. A final project report