Quizzma Latest Questions

Being prepared to do a complete job of developing and finalizing the scope baseline requires that you have done a thorough and timely job of Iding and analyzing stakeholder, and of collecting requirements. The development of the scope baseline can best be described as involving

Anonymous

Being prepared to do a complete job of developing and finalizing the scope baseline requires that you have done a thorough and timely job of Iding and analyzing stakeholder, and of collecting requirements. The development of the scope baseline can best be described as involving

A. the functional managers

B. the project team

C. all the stakeholders

D. the business analyst




Leave an answer

Leave an answer

2 Answers

  1. B. The project team is responsible for developing the scope baseline after getting input from key stakeholders.

  2. The development of the scope baseline can best be described as involving:

    C. all the stakeholders

    This is because developing a comprehensive scope baseline requires input and agreement from all stakeholders to ensure that the project requirements are accurately captured and aligned with the project’s objectives. This includes understanding the needs and expectations of everyone impacted by the project, ensuring that the scope is clearly defined and agreed upon.

Related Questions