“After determining that a change is needed, a project manager takes the following steps: 1. Issues formal change request 2. Communicates the change to all stakeholders. The PM discovers the communications approach did not satisfy stakeholders’ expectations. What should the PM do next?
A. Utilize the communications management and stakeholder engagement plans
B. Include stakeholders’ expectations in the project management plan
C. Communicate frequently with the project sponsor to track shareholders’ expectations
D. Review the communications management plan and release a status report”
A. Utilize the communications management and stakeholder engagement plans
Here’s why this option is the most appropriate:
Answer: A
Reason: The communications management and stakeholder engagement plan should be predictable, establish how communication will be managed and keep stakeholders engaged throughout.