After 7 months, a project has a CPI of .80 and it's trending down. What should the PM do next in this case?

Anonymous

After 7 months, a project has a CPI of .80 and it’s trending down. What should the PM do next in this case?

A. Issue a change request for cost re-baseling.

B. Issue a change request for additional resources.

C. Crash the project schedule.

D. Use the management reserve




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. A. Issue a change request for cost re-baseling.

    CPI of .80 is already over budget and trending down. The baseline is badly off the mark and in need of correction.