After 7 months, a project has a CPI of .80 and it’s trending down. What should the PM do next in this case?
A. Issue a change request for cost re-baseling.
B. Issue a change request for additional resources.
C. Crash the project schedule.
D. Use the management reserve
A. Issue a change request for cost re-baseling.
CPI of .80 is already over budget and trending down. The baseline is badly off the mark and in need of correction.