A project manager’s primary resonsibility is to deliver the product of the project within project constraints. Actions taken and changes made to the benefit of one constraint could negatively affect another. Which of the following describes the major constraints on a project?
A. Scope, number of resources, cost
B. Scope, cost, schedule
C. Scope, cost schedule, quality, risk, resources, customer satisfaction,
D. Schedule, cost, number of changes
C. Scope, cost schedule, quality, risk, resources, customer satisfaction