A project has the following characteristics: A new project stakeholder has been IDed. The new stakeholder is not actively participating and needs to be further engaged. What should PM do?

Anonymous

A project has the following characteristics: A new project stakeholder has been IDed. The new stakeholder is not actively participating and needs to be further engaged. What should PM do?

A. Review and update the stakeholder engagement plan

B. Inform the new stakeholder of both the project schedule and the specific assigned tasks

C. Ask the functional manager to send this new stakeholder to all relevant meetings

D. Have the new stakeholder partner with a more experienced stakeholder as a mentor




Related Questions

Leave an answer

Leave an answer

1 Answer

  1. A. The stakeholder engagement plan is updated as necessary to reflect changes in the stakeholder community. All other options are actions which are taken without assessment.