Quizzma Latest Questions

A highway renewal project you are manageing appears to have some missing scope. Your understanding of the scope was that the higheway was to be resurfaced. Now, one of the construction foremen has coe to ask why he finds no mention of repainting the lines on the repaved road. He also wants to know if there are any guard rail replacement work packages in the pojrect. you have seen some of the resurfaced road that is completed, with the new lines painted on them. Which of the following is most likely to have caused the misinterpretation of the project scope statement?

Anonymous

A highway renewal project you are manageing appears to have some missing scope. Your understanding of the scope was that the higheway was to be resurfaced. Now, one of the construction foremen has coe to ask why he finds no mention of repainting the lines on the repaved road. He also wants to know if there are any guard rail replacement work packages in the pojrect. you have seen some of the resurfaced road that is completed, with the new lines painted on them. Which of the following is most likely to have caused the misinterpretation of the project scope statement?

A. Imprecise language

B. Poor pattern structure, and chronological order

C. Variations in size of work packages or detail of work

D. too much detail




Leave an answer

Leave an answer

Related Questions