Which of the following statements regarding system and integration testing are NOT valid?

Which of the following statements regarding system and integration testing are NOT valid? 1.System testing is the last test phase before user acceptance testing.
2.System testing evaluates the complete system of integrated components working together against the documented requirements.
3.Integration testing tests the interactions between individual components of a software system.4
4.System testing must begin once most components are code complete.
5.Integration testing is completed before system testing can begin.




Leave an answer

Leave an answer

What is the capital of Egypt? ( Cairo )

1 Answer

  1. The statement that is NOT valid is 4. System testing must begin once most components are code complete.

    Explanation: While it is important for many components to be ready for system testing, system testing can begin even if not all components are fully complete, as long as a functional part of the system can be tested. In contrast, integration testing must occur first to ensure that components work together before completing system testing.