Two PMs have just realized that they are in a weak matrix organization and that the power as PMs is quite limited. One figures out that he is really a project expediter, and the other realizes she is really a project coordinator. How is a project expeditor different from a project coordinator?

Two PMs have just realized that they are in a weak matrix organization and that the power as PMs is quite limited. One figures out that he is really a project expediter, and the other realizes she is really a project coordinator. How is a project expeditor different from a project coordinator?

A. The PE cannot make decisions.

B. The PE can make more decisions

C. The PE reports to a higher-level manager

D. The PE has some authority

1 Answer

Verified archive
AnonymousJune 3, 2024

The coordinator reports to a higher-level manager and has some authority.

A. The PE cannot make decisions.